Olsen Avenue road upgrade, Gold Coast

This project targeted long-term batter stabilisation spanning a 2,500m2 site with extremely poor soil. Hydroganics delivered a superior, topsoil-free solution to the originally-specified use of imported topsoil and double-pass hydromulch. Cover crop and native seeds were injected as the organics were applied at a rate of 100m3/ha. The site quickly stabilised, native species germinated within three weeks. Within 20 months, natives were flourishing with extensive germination up to 3m tall.

Olsen Avenue - Pre-application
Olsen Avenue - Pre-application Olsen Avenue - Post-application Olsen Avenue - After 1 Week Olsen Avenue - After 2 Weeks Olsen Avenue - After 3 Weeks Olsen Avenue - After 12 Months